COVELO, Mendocino County, California — November 25, 2026. Mendocino County supervisors have taken a new step toward replacing the collapsed Hill Road bridge over Mill Creek near Covelo: at their November 17 meeting, the board voted 4–1 to select Granite Construction’s bid despite a protest from a competing contractor. The disputed award concerns County Transportation Contract 260021, a project whose original bridge failed on June 12, 2026.
Cover image: illustrative bridge over water by Rezuanur Rahman Mubin / Unsplash; not the damaged Green Bridge in Covelo or its planned replacement.
What the vote does and does not mean
The County’s published agenda identifies the crossing as Bridge 10C0111, Hill Road (County Road 327B) at milepost 2.05. The selected construction bid was approximately $6.31 million, according to local reporting on the board action, but award of the bid should not be mistaken for reopening of the crossing or completion of construction. The county’s transportation director was expected to sign the final agreement after required reviews.
Why there was a contractor dispute
Granite was the low bidder among seven firms. Its original bid did not name the steel-bridge manufacturer, a requirement contested by another bidder, Gordon N. Ball. Granite supplied the manufacturer’s name shortly after bids were opened. The Board decided to accept the bid despite the omission. One supervisor, Ted Williams, opposed the action, as explained in the November 23 report by The Mendocino Voice. The county’s own agenda includes the proposed award resolutions and transportation director’s correspondence in the public record.
What this means for drivers
The collapsed bridge has kept part of Hill Road unavailable since June, complicating trips into and out of the east side of Round Valley. Do not drive around the closure or assume a contract award provides a travel reopening date. Our earlier Covelo News report explains the existing closure and detour information. Consult Mendocino County Transportation or posted traffic controls for current access.
The agency’s project materials anticipate replacement work continuing into 2027; construction and opening dates depend on completed contracts, fabrication, weather and inspection. A target schedule is not a guaranteed reopening date.
Sources and documents
Official county agenda and bid-protest record: Mendocino County Board of Supervisors, file 26-1029, November 17, 2026. Meeting outcome and vote: The Mendocino Voice, Roger Coryell, November 23, 2026. This report does not represent a site inspection or confirmation that the bridge has reopened.
Support Covelo News
Choose how to support Covelo News:
Credit / Debit Card via StripeChoose your contribution amount on the secure California58 Stripe checkout. One-time support for independent local journalism.
Continue with PayPal Continue with ZelleZelle payments go to Vitaly Ataev Troshin. Please verify the recipient in your bank before sending. Availability depends on your bank.
Optional reader support. When possible, add “Covelo News” to the payment note. Contributions are not advertised as tax-deductible. Support does not influence editorial decisions.More from Covelo News
- Covelo’s Tribal Winds Phase 5 Advances: Round Valley Housing Authority Plans 18 Rental Homes by Mid-2027 →
- Covelo’s Mill Creek Bridge on Hill Road Remains Closed: County Publishes Detour Options →
- Thanksgiving in Covelo: A short outing to Round Valley Public Library exterior →
- Firefighters Contain Covelo Logan Lane Blaze Involving Two Mobile Homes, Initial Reports Say →
- Documentary Film Series Returns to Covelo’s Round Valley Library November 13 →